Daily Deck Blogging – 4/3/07

The contractor started on the deck today! We didn’t expect they’d start this soon (we thought it might be another 10 days), but I was glad to see them. They expect to be done next Monday (it takes about five working days to build a standard deck).

Deck deconstructed (or pre-constructed), beginning of day one:

View of the deck-in-progress from the sliding glass doors, end of day one:

View from the driveway, end of day one:

OK, it doesn’t look like that much happened the first day. Putting in the piece under the door that will help attach the deck to the house takes a while. They also cut a fair amount of wood during the day for later in the week. I expected the posts would be installed first, but they said the post installation is a day two job.